Transmission and Storage Upside
Q: Shahriar Pourreza with Wells Fargo asked when the identified transmission and storage opportunities will start to accrete to the growth rate and how to frame the inflection point.
A: Carim Khouzami explained that transmission projects take three to seven years to construct and roll into the plan, while battery storage projects have a much shorter duration of under three years from approval to operation.
Q: Shahriar Pourreza with Wells Fargo asked how much of the 1.5 to 3.5 gigawatts of storage opportunity sits in jurisdictions where Exelon already owns storage and where it is concentrated.
A: Carim Khouzami stated the pipeline is across all states, with a large portion in Maryland, Delaware, and New Jersey where utility ownership is currently permitted, while advocating for legislative changes in other states.
PJM Capacity Auction and Large Load Developments
Q: Paul Zimbardo with Jefferies asked about expectations for the May PJM auction and whether Exelon is advocating for price caps.
A: Colette Honorable responded that Exelon continues to support the use of price caps in the short and medium term to help manage high customer costs until more capacity is online.
Q: Paul Zimbardo with Jefferies asked if large load customers are willing to put up more upfront capital to reduce prospective equity needs.
A: Calvin Butler stated that developers are willing to step up, noting that collateral received for transmission security agreements has increased to take out speculative load and protect existing customers.
Pennsylvania Regulatory Outlook
Q: Carly Davenport with Goldman Sachs asked for precision on timing for another PECO rate case and key considerations in formulating the filing.
A: Michael Innocenzo stated that PECO is engaged with stakeholders and the ratemaking working group, and will ensure investments add value to the community before filing.
Q: Carly Davenport with Goldman Sachs asked about the reduction in the overall large load pipeline from 25 to 23 gigawatts.
A: Rob Kleczynski explained that the reduction reflects the cluster study process working as projects drop out for various reasons.
Large Load Timeline and Financing
Q: Nicholas Amicucci with Evercore ISI asked if the 11 gigawatts of high probability loads are reflected in the current plan and what energization schedule underpins it.
A: An unnamed executive stated that a small amount is in the current plan, with about 10% coming online by 2028 and three quarters of the 11 gigawatts online through 2034.
Q: Nicholas Amicucci with Evercore ISI asked how to think about the financing path for incremental capital opportunities.
A: Calvin Butler reiterated a balanced approach, with approximately 40% of incremental capital opportunities funded by equity, supplemented by build-own-transfer arrangements for large batteries as explained by Carim Khouzami.
Capital Allocation Across Jurisdictions
Q: Jeremy Tonet with JPMorgan Securities asked how Exelon thinks about shifting capital across different states and managing the ComEd proceeding.
A: Rob Kleczynski noted that transmission capital has grown at 16% and that trend is expected to continue alongside storage upside, while Calvin Butler highlighted the power of Exelon's platform to shift capital where needed.